Plymouth Educational Center Modular Classrooms

Client:  Plymouth Educational Center

Partner:  EMOD, LLC

Challenge:  Plymouth Educational Center needed to add a complex of  modular classrooms to accommodate a 9th Grade Academy  necessitated by booming enrollment.  The addition to the school needed to be completed in less than 5 weeks in the field.

Solution:  The client selected EMOD and Mark Line to design a cost-effective solution which used concurrent construction (buildings were fabricated off-site while site development and foundations were installed in the field) to deliver the project on the aggressive schedule dictated by the client.